15A NCAC 05B .0113      RESPONSE DEADLINE TO DEPARTMENT'S REQUEST(S)

An applicant or permittee shall submit to the Department supplemental information regarding an application for a new permit, modified permit, or permit renewal within 180 days after the date of receipt of the Department's written request(s) for such information.  Upon written request of the applicant or permittee to the Director, an additional reasonable specified period of time not to exceed one year shall be granted upon determination of good cause by the Director.  Additional time may be granted by the Mining and Energy Commission, provided written request is made by the applicant or permittee before the expiration of the one‑year period.

 

History Note:        Authority G.S. 74‑51; 74‑52; 74‑63; 143B‑290;

RRC Objection Eff. September 15, 1994 due to lack of statutory authority;

Eff. November 1, 1994;

Amended Eff. August 1, 2012 (see S.L. 2012-143, s.1.(d)).